Reinforced Concrete Slab and Formworks
3 Weeks to complete
Construction of Formwork including Dowell bars and installation of steel mesh. Arrangement of all plant, labour materials. Construction and install reinforced concrete slab covering 285m3. Located in a difficult area in terms of logistics although Project was delivered on time due to correct planning.